This guide is for Brisbane homeowners about to renovate, extend, raise or build, who keep hearing “the certifier will sort that out”. A building certifier plays a big part in your project, but it’s a narrower part than most people expect. Knowing where their job starts and stops saves a lot of frustration, especially when something goes wrong.
The short version
In Queensland, building certifiers are licensed by the Queensland Building and Construction Commission (QBCC). They can work for a council or in private practice. Their core job is to:
- assess building applications and decide whether to issue a building approval
- inspect the work at set stages
- certify that the work complies with the building rules and the approval
- issue enforcement notices where needed
- issue the final paperwork that lets the building be used.
Certifiers must act in the public interest and follow a Code of conduct. That’s an important point: even if you pay the fee, the certifier isn’t your advocate. They’re there to make sure the building meets the law.
Building approval vs planning approval
These are two different approvals, from two different places, about two different questions.
| Planning approval | Building approval | |
|---|---|---|
| Who decides | Your council (Brisbane City Council for most of Brisbane) | A building certifier, private or council |
| The question | What can be built here, and where? Zoning, overlays, character, flood, height, setbacks | Is the building itself safe and compliant? Structure, fire safety, health and amenity, energy efficiency |
| Rules used | The local planning scheme (Brisbane City Plan 2014) | The National Construction Code and Queensland Development Code |
| Needed for | Only some projects | Most building work, including extensions, raising and renovations |
The order matters. A private certifier can’t issue a building approval until other necessary approvals, such as a town planning approval from council, have been given. If your project needs a development application, that comes first.
For houses in Brisbane, a private certifier is usually the assessment manager for the building application. Where a design doesn’t meet the standard siting rules (for example a boundary setback), the certifier can ask Council for a referral agency response.
Who hires the certifier
QBCC says your builder will usually engage the certifier on your behalf, but you can appoint one directly. Your building contract should say who is responsible.
A few rules apply either way:
- The engagement must be in writing and state the certification fee.
- If someone other than you (such as your builder) engages the certifier, the certifier must send you a Form 18 notice with their details and responsibilities within 15 business days.
- Ending an engagement part way through isn’t as simple as sacking a tradie. The Building Act sets a process, so ask how it works before you sign.
The inspections for a house
For a new single detached house (a class 1a building), the Building Regulation 2021 sets mandatory inspection stages:
- Excavation, before footings or slab concrete is poured
- Footings, if the house has footings, after formwork and reinforcement are in
- Slab, if the house has a slab, after formwork and reinforcement are in
- Frame
- Final, checking outstanding items and collecting certificates such as termite protection, wet area waterproofing, glazing, smoke alarms and energy efficiency.
For class 10 buildings and structures, such as garages, sheds and carports, the only mandatory stage is the final, other than swimming pools. A building approval can add extra stages, so read yours.
It’s the builder’s job to tell the certifier when work is ready for inspection. After a satisfactory stage inspection the certifier signs a Form 16 inspection certificate. For some aspects, a certifier can rely on a “competent person”, such as an engineer, to inspect and certify.
Your rights as the owner
- Copies of inspection documents. Before the final stage you can ask for inspection documentation for earlier stages using Form 35. The certifier must provide it within 5 business days.
- Extra inspections. If your certifier was engaged on or after 1 October 2020, you can request additional certifying functions using Form 31. You must give the notice to whoever engaged the certifier within 10 business days of being told the certifier’s details, and you pay the reasonable cost.
- Records. Private certifiers must keep inspection documentation for at least 7 years after the work is completed.
If your builder engages the certifier, put a note in your diary the day you receive the Form 18. You only have 10 business days from being told the certifier’s details to request extra inspections with a Form 31.
The final certificate
For a house (class 1a) and class 10 structures, the end point is a final inspection certificate (Form 21). The certifier must personally sign it. QBCC says the certifier must give you the final inspection certificate plus copies of the other inspection documentation within 5 business days. You don’t need to ask for it.
Other building classes get a certificate of occupancy instead.
Keep the Form 21, your approved plans and the inspection certificates together. If you sell or renovate again, you’ll want to show that the work was approved and signed off.
What certifiers don’t do
QBCC lists what building certifiers don’t do. It’s a list every homeowner should read before the job starts.
- Design. Certifiers must not design the building or carry out any of the work. Your designer, architect or engineer does that.
- Supervise the site. They visit at inspection stages. They aren’t there day to day.
- Quality control and finishes. Paintwork, the wrong coloured timber, a wonky cornice: not the certifier’s job.
- Enforce your contract. Whether the builder is complying with your contract, or a subcontractor with theirs, is outside their role.
- Site safety. Workplace health and safety on site is regulated separately.
- Pay other agencies’ fees. Referral agency and council fees aren’t theirs to cover.
In plain terms: a certifier’s sign-off means the work met the legal minimum at the stages inspected. It isn’t a quality guarantee, and it isn’t a warranty.
When something goes wrong
Work out what the problem is about, then go to the right place.
- Defects, incomplete work, delays or payment disputes with your builder. Raise it with the builder in writing first. If that fails, QBCC has a separate complaints and disputes process for contractors.
- The certifier’s conduct. If you believe a certifier has engaged in unsatisfactory conduct or professional misconduct in performing certifying functions, you can lodge a complaint with QBCC. It must be against an individual certifier, not a company, include evidence and be supported by a statutory declaration.
QBCC’s certification team can’t regulate contracts between certifiers and other parties, such as refunding certification fees. It also generally doesn’t investigate communication style or slow email replies. Time limits apply to complaints. For work under a building development approval, the limit is generally 7 years after the final inspection certificate or certificate of occupancy.
Checklist: working with a certifier
- Confirm in your contract who engages the certifier.
- Check the certifier’s licence on the QBCC register.
- Read the engagement agreement: fee, inspections included, extra charges.
- Sort out any planning approval before expecting building approval.
- Diarise Form 18 timing and your Form 31 deadline.
- Ask for copies of stage inspection certificates as you go (Form 35).
- Collect the Form 21 and all inspection documents at the end.
- Keep everything with your approved plans.
Questions to ask a certifier
- Who is the individual licensed certifier on my job, and what’s their licence number?
- What inspections does your fee cover, and what costs extra?
- Does my project need planning approval first?
- Will we need a referral agency response from Council for siting?
- Which aspects will you rely on competent persons (such as an engineer) to certify?
- What documents do you need from me or my builder before the final?
Common mistakes
- Expecting the certifier to check workmanship or finishes.
- Assuming the certifier will step in on a contract or payment dispute.
- Starting work before the building approval is issued.
- Missing the 10 business day window for requesting extra inspections.
- Losing the Form 21 and inspection paperwork.
Who to talk to
Through the Build in Brisbane directory you can find:
- Building certifiers for building approval and inspections
- Town planners if your project also needs council planning approval
- Building designers and drafting services for approval drawings
- Engineers for structural design and certification
- Builders who can explain how they manage inspections on their jobs.
Sources
- QBCC: Role and responsibilities of a certifier
- QBCC: Council or certifier, who approves what?
- Business Queensland: Role of building certifiers
- Business Queensland: Stages of a building inspection
- Business Queensland: Working with building certifiers
- Business Queensland: Building forms (Forms 16, 18, 21, 31, 35)
- Form 18: Notice to the owner that a private certifier has been engaged (PDF)
- Queensland Government: Inspection guideline for class 1 and 10 buildings (PDF)
- QBCC: Complaint against a certifier
- Brisbane City Council: Extensions, raising or renovations
- Building Act 1975 (Qld) s 144: Restriction on discontinuing engagement
This guide is general information only, not legal advice. Building rules and forms change. Check current requirements with QBCC, Business Queensland or your certifier for your specific project.